Stena Baltica - New Air Cooler

Stena Baltica’s MAN B&W 9L48/60B main engine required a new air cooler by a fixed date. Standard manufacturer lead times made the deadline unworkable. FARAD S.A. produced and delivered the unit in 15 working days, a day ahead of schedule.

New air cooler manufactured for Stena Baltica's main engine

Challenge

A hard delivery deadline of 23 December left no margin for the lead times quoted by other manufacturers.

Engineering Solution

  1. Confirmed specification against the MAN B&W 9L48/60B’s cooling duty and mounting
  2. Manufactured with FARAD S.A. for compatibility across major marine engine platforms
  3. Shipped to meet the fixed 23 December deadline

Customer

Stena Line

Vessel

Stena Baltica

Vessel type

RoPax Ferry

Equipment

Air Cooler

Scope

Supply

Turnaround

15 Working Days

Related services

Discuss a similar project