Madicken - Air Conditioning Repair

BreezeMarine engineers restored normal operation of the air conditioning system aboard M/V Madicken at the Port of Paljassaare, Tallinn, on 23-24 September 2026.

Challenge

The vessel’s air conditioning system needed leak detection and fault finding.

On inspection, our technicians traced the refrigerant leak to a faulty supply valve and found the existing refrigerant hoses corroded. The instrumentation was due for renewal at the same time, so the repair grew into a wider overhaul that had to be finished within the vessel’s port stay.

Engineering Solution

  1. Inspected the system and traced the leak to the supply valve.
  2. Replaced the leaking supply valve and the filter drier
  3. Replaced the corroded refrigerant hoses
  4. Replaced the pressure gauges, pressure switches and oil pressure switch
  5. Installed service valves on the instrument lines
  6. Charged the system with refrigerant and confirmed tightness with a leak test
  7. Tested the system in operation and handed it over to the crew within 2 working days

Customer

Forsa Juru Agentura UAB

Vessel

M/V South

Vessel type

General Cargo

Equipment

Air Conditioning System

Scope

Leak Detection, Fault Finding and Repair

Turnaround

2 Working Days